Otter Creek Bridge Revised Schedule
The reconstruction of the Otter Creeki Bridge on Stones Pocket Road has been delayed to Spring of 2027. Due to DNR restrictions on in-stream disturbances from March 15 to June 1, the demo will begin in late February with construction of the abutments to be completed by March 15. Weather pending, the bridge deck will be poured in April with the remaining work to follow.